How far ahead must a person call a One Call Notification Center before digging 16 inches or deeper using mechanical equipment?

Study for the TCEQ On-Site Sewage Facilities (OSSF) Test. Learn with targeted flashcards and in-depth multiple-choice questions complete with hints and explanations. Start preparing today for a successful exam experience!

In Texas, when planning to dig 16 inches or deeper using mechanical equipment, it is essential to provide advance notice to the One Call Notification Center to ensure safety and compliance with regulations. The correct requirement is to call at least two working days before starting the excavation. This notice allows utility companies adequate time to locate and mark underground utilities, helping to prevent accidental damage to vital infrastructure, which could lead to dangerous situations or significant service interruptions.

The two-working-day notice requirement is a safeguard for both the excavator and nearby residents or businesses. It facilitates the necessary coordination and ensures that all parties are informed about the presence of underground utilities in the area of the proposed digging. Understanding this timeline is crucial for anyone involved in excavation work to ensure adherence to legal regulations and to promote safe working environments.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy